Skip navigation

DSpace

機構典藏 DSpace 系統致力於保存各式數位資料(如:文字、圖片、PDF)並使其易於取用。

點此認識 DSpace
DSpace logo
English
中文
  • 瀏覽論文
    • 校院系所
    • 出版年
    • 作者
    • 標題
    • 關鍵字
  • 搜尋 TDR
  • 授權 Q&A
    • 我的頁面
    • 接受 E-mail 通知
    • 編輯個人資料
  1. NTU Theses and Dissertations Repository
  2. 法律學院
  3. 法律學系
請用此 Handle URI 來引用此文件: http://tdr.lib.ntu.edu.tw/jspui/handle/123456789/4017
標題: 公共工程物價調整規定與情事變更原則之比較研究
The Comparative Study on the Price Adjustment Regulations and the Principle of Change of Circumstances in Public Construction
作者: Hsin-Hung Tu
杜欣鴻
指導教授: 詹森林
關鍵字: 情事變更原則,營造工程物價指數,營建物價,物價調整處理原則,工程採購契約範本,合理預見範圍,
Doctrine of Change of Circumstances,Construction Cost Index,Construction Cost,Principles of Payment Adjustment on the Price of Materials,Model Contract for Engineering Procurement,The Range Reasonably Foreseeable,
出版年 : 2016
學位: 碩士
摘要: 在公共工程實務上,廠商往往因為資金或風險等考量,不會在工程起初即購買全部施工物料,而是分期購買,因而公共工程契約之雙方當事人勢必面臨施工期間內營建物料價格變動之風險。而公共工程契約通常標的金額龐大,其施工物料價格變動所牽涉之價金少則幾百萬多則數十億,對廠商或機關而言影響至鉅,故物價變動可否請求調整工程款,實為公共工程領域之常見紛爭。
鑑於此,公共工程契約之其中一方當事人在調解、仲裁未果後,往往以民法情事變更原則作為請求權基礎而向法院起訴,而行政機關因應當時之物價劇烈變動,亦陸續頒佈了一系列的物價調整規定,肯認在公共工程契約下,於營建物料價格上漲時廠商可向機關請求調整工程款;於營建物料價格下跌時機關亦可向廠商扣減工程款,使物價變動而生之風險能被雙方公平合理的分擔。
惟一系列之物價調整規定頒佈後,有關公共工程物價調整之爭議仍未減少,究其原因實為民法情事變更原則與物價調整規定本身適用上之疑義,以及兩者間之適用爭議未予釐清。因而本文乃就民法情事變更原則與物價調整規定各自之常見疑義予以整理,並提出本文見解,另就該兩者間之適用爭議,則分析歸納實務判決,嘗試將實務判決常提及之「合理預見範圍」的概念具體化,並認為現行工程採購契約範本之物價調整規定應強制納入公共工程契約。
In the practice of public construction, due to the concern of cash flow and potential risks that may occur, the contractors would commonly refuse to purchase all the materials needed at the very beginning of the construction. The purchases will rather be conducted in accordance with its progress. Therefore, the parties of the public construction contract, will bear the risk of price fluctuation of the materials during the construction. Such risk is bound to be tremendous. As the large amounts of money involved in a construction, the increase of expenses caused by the price fluctuation of construction materials, which may range from millions to billions, will have significant impact on both the contractor and the owner-builder. Therefore, whether or not the price fluctuation can be a justifiable ground for the parties to make a payment adjustment, becomes a common dispute in the field of public construction.
Normally, the parties would settle such dispute in mediation or arbitration. Failing that, the party which is unsatisfied with the given result would file a lawsuit pleading for adjustment of the payment on the ground of change of circumstances, which is stipulated in Article 227-2 of the Taiwan Civil Code. Additionally, to respond to the then drastic price fluctuation of construction materials, the Public Construction Commission, Executive Yuan issued a series of Principles of Payment Adjustment on the Price of Materials successively. On the one hand, the Principles affirmed the contractor’s right to request the owner-builder to adjust the payment when the price of construction materials rises. On the other hand, it also affirmed the owner-builder’s right to reduce the payment when the price falls. Such principles are aiming at fairly distributing the risk of price fluctuation to the parties.
However, the disputes of payment adjustment on the price fluctuation of construction materials appear undiminished even after the issuing of the said Principles. The main reason is under which situation could Article 227-2 of Taiwan Civil Code and the Principle of Payment Adjustment on the Price of Materials be adopted remain unclear. Besides, the contradiction between the law and the Principles remain unsolved, either. Aiming at clarifying the ambiguities, this thesis categorizes the common ambiguities of Article 227-2 of Taiwan Civil Code and the Principle of Payment Adjustment on the Price of Materials respectively, then provides possible solutions. Furthermore, dealing with the contradiction between the law and the Principles, this thesis analyzes and induces the court opinions from the relevant judgments, and attempts to describe the meaning of a commonly raised standard - “the Range Reasonably Foreseeable”. The position of this thesis is that, the provisions of payment adjustment on the price of materials stipulated in the current Model Contract for Engineering Procurement should be included in all the public construction contracts.
URI: http://tdr.lib.ntu.edu.tw/jspui/handle/123456789/4017
全文授權: 同意授權(全球公開)
顯示於系所單位:法律學系

文件中的檔案:
檔案 大小格式 
ntu-105-1.pdf2.57 MBAdobe PDF檢視/開啟
顯示文件完整紀錄


系統中的文件,除了特別指名其著作權條款之外,均受到著作權保護,並且保留所有的權利。

社群連結
聯絡資訊
10617臺北市大安區羅斯福路四段1號
No.1 Sec.4, Roosevelt Rd., Taipei, Taiwan, R.O.C. 106
Tel: (02)33662353
Email: ntuetds@ntu.edu.tw
意見箱
相關連結
館藏目錄
國內圖書館整合查詢 MetaCat
臺大學術典藏 NTU Scholars
臺大圖書館數位典藏館
本站聲明
© NTU Library All Rights Reserved