請用此 Handle URI 來引用此文件:
http://tdr.lib.ntu.edu.tw/jspui/handle/123456789/99799| 標題: | 台灣電力市場的未來挑戰:夜尖峰供需缺口與備用容量率之預估 Forecasting the Supply-Demand Gap and Reserve Margin in Taiwan’s Electricity Market |
| 作者: | 李佳濰 Chia-Wei Lee |
| 指導教授: | 洪茂蔚 Mao Wei Hung |
| 關鍵字: | 能源政策,電源開發計劃,備用容量率,能源轉型,電力供給, power-generation development plan,energy policy,reserve margin,energy transition,power supply, |
| 出版年 : | 2025 |
| 學位: | 碩士 |
| 摘要: | 在「算力即國力」趨勢驅動下,人工智慧(AI)與高效能資料中心對電力的全天候需求急遽攀升。這些負載多為全天候用電需求, 晚間運行時將與太陽光電發電高峰出現時序錯配,進一步壓縮台灣本就吃緊的夜尖峰供電餘裕。
研究方法:係整合歷年 《全國電力資源供需報告》 與 《長期電源開發計畫》,納入機組歲修、退役排程與招標延宕,並結合高科技產業擴產資訊,建立 10 年期夜尖峰供需模型,追蹤備用容量率變動。 需求面分析顯示, 半導體先進製程與 AI 雲端資料中心屬 24 小時高負載 ,其新增電力需求在 2030 年前占全國增量 82%,帶動夜尖峰負載自 2024 年的 3,725 萬瓩升至 2033 年的 4,766 萬瓩, 十年間成長 31.8% 。供給面挑戰則包括,離岸風電 Round 3-1(2,335 MW)統一展延至少一年,Round 3-2 最快 2028 年後才陸續併網,顯示官方容量時程偏樂觀;以及大林、通霄、協和等燃煤轉燃氣計畫接連流標或重議價,導致燃氣機組上線時程普遍落後。 系統現況方面 ,台電備轉容量率雖因新機組與儲能併網略升至 7–11%, 仍低於國際建議值 10–15% ; 歷次大停電事件暴露備援脆弱 ,任何大型機組故障都可能觸發限電。模型結果指出,在離岸風電延宕與燃氣機組遲滯的基準情境下,夜尖峰備用容量率將長期滯留 6–7% 警戒邊緣。 Propelled by the maxim that “computing power is national power,” round-the-clock electricity demand from artificial-intelligence (AI) applications and high-performance data centers is surging. Because these loads run 24/7, their night-time consumption is chronically out of phase with solar output, further squeezing Taiwan’s already-tight night peak reserve margin. We synthesize historical National Power Supply–Demand Reports and Long-Term Power Development Plans, incorporate maintenance and retirement schedules, tender delays, and high-tech industry expansion timelines, and construct a ten-year night-peak supply-demand model that tracks reserve-margin dynamics. On the demand side, advanced semiconductor fabs and AI cloud data centers are continuous high-load users. Their incremental power needs will account for 82 % of national load growth before 2030, driving night-peak demand from 37.25 GW in 2024 to 47.66 GW in 2033—a 31.8 % increase. On the supply side, the Round 3-1 offshore-wind (2,335 MW) has been uniformly deferred by at least one year, while Round 3-2 will not reach commercial operation until 2028 at the earliest, indicating that official capacity timelines are overly optimistic. Coal-to-gas conversions at Talin, Tunghsiao, and Xiehe have repeatedly failed tenders or required repricing, pushing gas-fired units behind schedule. Although Taipower’s operating reserve margin ratio has edged up to 7–11 % with new units and energy storage systems coming online, it remains below the 10–15 % internationally recommended range. Past blackouts reveal fragile backup capacity: a single large-unit failure can trigger load-shedding. Model results show that, under baseline assumptions of offshore-wind delays and gas-unit slippage, night-peak reserve margins will hover at a precarious 6–7 % throughout the decade. |
| URI: | http://tdr.lib.ntu.edu.tw/jspui/handle/123456789/99799 |
| DOI: | 10.6342/NTU202501480 |
| 全文授權: | 未授權 |
| 電子全文公開日期: | N/A |
| 顯示於系所單位: | 國際企業學系 |
文件中的檔案:
| 檔案 | 大小 | 格式 | |
|---|---|---|---|
| ntu-113-2.pdf 未授權公開取用 | 2.91 MB | Adobe PDF |
系統中的文件,除了特別指名其著作權條款之外,均受到著作權保護,並且保留所有的權利。