  1. NTU Theses and Dissertations Repository
  2. 工學院
  3. 土木工程學系
Please use this identifier to cite or link to this item: http://tdr.lib.ntu.edu.tw/jspui/handle/123456789/8814
Full metadata record
???org.dspace.app.webui.jsptag.ItemTag.dcfield???ValueLanguage
dc.contributor.advisor謝尚賢
dc.contributor.authorZoe Leeen
dc.contributor.author李美儀zh_TW
dc.date.accessioned2021-05-20T20:01:51Z-
dc.date.available2011-08-18
dc.date.available2021-05-20T20:01:51Z-
dc.date.copyright2011-08-18
dc.date.issued2011
dc.date.submitted2011-08-17
dc.identifier.citationAdeli, H., and A. Karim, (1997). 'Scheduling/Cost Optimization and Neural Dynamics Model for Construction.' Journal of Construction Engineering and Management 123(4): 450-458.
Ammar, M. A., and E. Elbeltagi, (2001). 'Algorithm for Determining Controlling Path Considering Resource Continuity.' Journal of Computing in Civil Engineering 15(4): 292-298.
Dzeng, R. J., H. P. Tserng, and W. C. Wang, (2005). 'Automating schedule review for expressway construction.' Journal of Construction Engineering and Management-Asce 131(1): 127-136.
Edmund, N., J. Chrzanowski, and D. W. Johnston, (1986). 'Application of Linear Scheduling.' Journal of Construction Engineering and Management 112(4): 476-491.
Edwards, P. J. and P. A. Bowen, (1998). 'Risk and risk management in construction: a review and future directions for research.' Engineering Construction and Architectural Management 5(4): 339-349.
Fan, S. L. and H. P. Tserng, (2006). 'Object-oriented scheduling for repetitive projects with soft logics.' Asce- Journal of Construction Engineering and Management 132(1): 35-48.
Gonzalez, V., L. F. Alarcon, S. Maturana, F. Mundaca, and J. Bustamante, (2010). 'Improving Planning Reliability and Project Performance Using the Reliable Commitment Model.' Asce- Journal of Construction Engineering and Management 136(10): 1129-1139.
Harris, R. B. and P. G. Ioannou, (1998). 'Scheduling Projects with Repeating Activities.' Journal of Construction Engineering and Management 124(4): 269-278.
Hassanein, A. and O. Moselhi, (2004). 'Planning and scheduling highway construction.' Asce- Journal of Construction Engineering and Management 130(5): 638-646.
Hong, T., K. Cho, and C. Hyun, (2010). 'Integrated Schedule and Cost Model for Repetitive Construction Process.' Journal of Management in Engineering 26(2): 78-88.
Huang, R.-y., and K.-S. Sun, (2009). 'A GA optimization model for workgroup-based repetitive scheduling (WoRSM).' Advances in Engineering Software 40(3): 212-228.
Hyari, K. H., K. El-Rayes, and Mohammad El-Mashaleh, (2009). 'Automated trade-off between time and cost in planning repetitive construction projects.' Construction Management and Economics 27(8): 749 - 761.
Ibbs, W., and L. D. Nguyen, (2008). 'FLORA: New forensic schedule analysis technique.' Asce- Journal of Construction Engineering and Management 134(7): 483-491.
Ipsilandis, P. G., (2007). 'Multiobjective linear programming model for scheduling linear repetitive projects.' Asce- Journal of Construction Engineering and Management 133(6): 417-424.
Long, L. D., and A. Ohsato, (2008). 'Fuzzy critical chain method for project scheduling under resource constraints and uncertainty.' International Journal of Project Management 26(6): 688-698.
Maravas, A., and J. P. Pantouvakis, (2010). 'A Fuzzy Repetitive Scheduling Method for Projects with Repeating Activities.' Journal of Construction Engineering and Management
Mattila, K. G., and A. Park, (2003). 'Comparison of Linear Scheduling Model and Repetitive Scheduling Method.' Journal of Construction Engineering and Management 129(1): 56-64.
Suhail, S. A., and R. H. Neale, (1994). 'Cpm/Lob - New Methodology to Integrate Cpm and Line of Balance.' Asce- Journal of Construction Engineering and Management 120(3): 667-684.
Tah, J. H. M., and V. Carr, (2001). 'Knowledge-based approach to construction project risk management.' Journal of Computing in Civil Engineering 15(3): 170-177.
Tamimi, S., and J. Diekmann, (1988). 'Soft Logic in Network Analysis.' Journal of Computing in Civil Engineering 2(3): 289-300.
Wang, C.-H., and M.-C. Wu, (1998). 'A multistage recursive algorithm for scheduling repetitive construction projects.' Journal of Chinese Institute of Civil and Hydraulic Engineering 10(1): 17-30.
Warner, F., (1993). 'Risk Analysis, Perception and Management - Royal-Soc-Grp.' Interdisciplinary Science Reviews 18(4): 397-397.
何霖(譯) K. Heldman(著) (2008). 'PMP專案管理認證指南 第四版.' 碁峰資訊股份有限公司.
呂守陞, 官良民, 歐陽偉, (2007). '污水下水道工程推進工法評估模式之研究.' 中華技術.
倪至寬 (2005). '衛生下水道施工與標準作業程序(上) ' 詹氏書局.
孫國勛 (2005). '工作群組式重複性專案排程與最佳化模式之研究.' 國立中央大學博士論文.
廖碧雲 (2006). '影響污水下水道管線工程工期因素與成本結構之分析.' 中華大學碩士論文.
蘇文哲 (2005). '應用MS Project於污水下水道專案管理-以台南市污水下水道管網工程為例.' 國立成功大學碩士論文.
dc.identifier.urihttp://tdr.lib.ntu.edu.tw/jspui/handle/123456789/8814-
dc.description.abstract污水下水道新建工程為典型之重複性工程。在實務上此種工程通常使用一般施工網圖進行排程,但一般之施工網圖並不易表達重複性工程之軟邏輯(soft logic),且此種工程在施工執行過程中常常遭受無法預知因素(例如:路證核准之延遲、民眾陳情、天氣不佳或地下障礙物等)之干擾,致使施工經常出現脫序作業現象,造成施工網圖的失真與現況不符,而此網圖必須仰賴人工修正,十分耗時費力。因此,本研究以風險控管角度,檢核工程之工作分解結構,提出簡化排程的流程與策略。此策略藉由簡化重複性工程排程組合變異,以分析關鍵工項的資源使用來建立軟邏輯作業關係和定義施工之工作面,並且在分析出專案排程策略後,根據關鍵工項的資源與優先順序產生施工排程。如此可以有效地考慮施工排程之軟邏輯,並提高排程的效率。zh_TW
dc.description.abstractThe pipe-jack projects are repetitive projects and may often be delayed by some unpredictable factors, such as underground barriers, bad weather condition, etc., while they are under construction. Usually the project network diagrams are used in these projects for their scheduling. However, the project network diagrams cannot easily handle the soft logics in repetitive projects. Also, the editing of them for synchronization with project changes is very time-consuming and labor-intensive. Therefore, this research proposes a scheduling strategy that identifies the key work items in WBS (Work Breakdown Structure) from the perspective of risk control, analyzes the resources associated with the key work items to define the soft logics and concurrent working processes, and then produces the scheduling results based on the resources and priority of the key work items. The proposed scheduling strategy can effectively account for the soft logics and allow for efficient scheduling for pipe-jack projects.en
dc.description.provenanceMade available in DSpace on 2021-05-20T20:01:51Z (GMT). No. of bitstreams: 1
ntu-100-R98521611-1.pdf: 4158519 bytes, checksum: 0387670a8e2453f1cb9caec842d6f48d (MD5)
Previous issue date: 2011
en
dc.description.tableofcontents摘要 i
Abstract ii
目錄 iii
圖目錄 v
表目錄 vii
第一章 緒論 1
1.1 研究背景與動機 1
1.2 研究目的 2
1.3 研究內容與範圍 4
1.4 論文架構 6
第二章 下水道工程特性之探討 7
2.1 施工工法簡介 7
2.2 重複性工程 10
2.3 工作分解結構 12
2.4 施工排程風險 17
第三章 下水道工程之排程邏輯準則與策略 20
3.1 工程時程控管法 20
3.2 排程邏輯準則 23
3.3 排程組合限縮策略 29
第四章 污水下水道工程案例探討 34
4.1 研究個案簡介 34
4.2 個案之風險與成本分析 37
4.2.1 試挖管遷 37
4.2.2 工作井沉設 40
4.2.3 推進到達口設施 42
4.2.4 推進施工 43
4.2.5 人孔收築 46
4.2.6 小結 48
4.3 以排程組合限縮法對污水下水道工程個案排程 51
4.4 案例網圖比較說明 56
第五章 下水道工程排程系統 60
5.1 Excel資料處理單元 61
5.2 CLIPS自動決策單元 65
5.3 Google Earth人工決策單元 69
5.4 MS Project排程展示單元 71
第六章 結論與建議 72
6.1 研究成果 72
6.2 個案之施工排程建議 73
6.3 其他重複性工程排程建議 74
dc.language.isozh-TW
dc.title下水道工程之施工排程策略研究zh_TW
dc.titleA Study on Scheduling Strategy for Pipe-Jacken
dc.typeThesis
dc.date.schoolyear99-2
dc.description.degree碩士
dc.contributor.oralexamcommittee呂守陞,范素玲
dc.subject.keyword重複性工程,排程策略,污水下水道工程,風險管控,排程邏輯,zh_TW
dc.subject.keywordScheduling Strategy,Pipe-Jack Projects,Repetitive Projects,Risk Control,Scheduling Logic,en
dc.relation.page82
dc.rights.note同意授權(全球公開)
dc.date.accepted2011-08-17
dc.contributor.author-college工學院zh_TW
dc.contributor.author-dept土木工程學研究所zh_TW
Appears in Collections:土木工程學系

Files in This Item:
File SizeFormat 
ntu-100-1.pdf4.06 MBAdobe PDFView/Open
Show simple item record


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.

社群連結
聯絡資訊
10617臺北市大安區羅斯福路四段1號
No.1 Sec.4, Roosevelt Rd., Taipei, Taiwan, R.O.C. 106
Tel: (02)33662353
Email: ntuetds@ntu.edu.tw
意見箱
相關連結
館藏目錄
國內圖書館整合查詢 MetaCat
臺大學術典藏 NTU Scholars
臺大圖書館數位典藏館
本站聲明
© NTU Library All Rights Reserved