dc.contributor.advisor | 曾惠斌(Hui-Ping Tserng) | |
dc.contributor.author | Po-Wen Chan | en |
dc.contributor.author | 詹博文 | zh_TW |
dc.date.accessioned | 2021-06-15T01:48:31Z | - |
dc.date.available | 2014-07-14 | |
dc.date.copyright | 2009-07-14 | |
dc.date.issued | 2009 | |
dc.date.submitted | 2009-07-06 | |
dc.identifier.citation | 英文參考文獻
1. 'Project control for construction.' (1987). Publication No. 6-5, Bureau of Engrg.Res., Univ. of Texas, Austin, Tex., Sep. 2. Adrian,James J.,”JimAdrian’s Construction Productivity Newsletter”, 5317N. Woodview Ave.,Peoria,Illinois,61614. 3. Bob McTague and George Jergeas,(2002)”Productivity Improvements on Alberta Major Construction Project”Construction Productivity Improvement Report/Project Evaluation Tool/May 4. Howell,G.A.(1999).”What is lean construction-1999.”Proc.,7th Annu.Conf. of Int. Group for Lean Constr.,I.D.Tommelein and G.Ballard,eds.,1-10. 5. James P.Womack,Daniel T.Jones,Daniel Roos,(1990)The Machine that changed the world 6. Jan A. Elfving,Iris D.Tommelein,Glenn Ballard(2004)”Improving the delivery process for engineered-to-order products-Lessons learned from power distribution equipment.”12th-annuel conference on lean construction(IGLC12), Copenhagen, Denmark, August 2004 7. Kerzner, Harold, (2001)”Project Management:A System Approach to Planning, Scheduling and Controlling”,6th Ed.,John Wiley&Sons,Inc.2001 8. Lauter,Alexander and Jenkins,Douglas G.,(1982)”Motivating Construction Workers”, Journal of Construction Division,ASCE,Vol.108,C04,December 1982. 9. Lincoln H.Forbes,Syed M.Ahmed(2004)”Aadpting lean construction methods for developing nations”,Emerging Technologies Track-Paper No.089 10. Salem,J.Solomon,A.Genaidy,and M.Luegring(2005)”Site Implementation and Assessment of Lean Construction Techniques”Lean Construction Journal 2005,Vol 2#2 October. 11. Ohno,T.(1987)Toyota Production System,Productivity Press,Portland,OR,USA. 12. Wang, H. J., Zhang, J. P., Chau, K.W., and Anson, M. (2004). “4D dynamic management for construction planning and resource utilization” Automation in Construction, Vol. 13, pp. 575-589. 13. Zaneldin, E., Hegazy, T., and Grierson, D. (2001). “Improving design coordination for building project” Construction Engineering and Management, Vol. 127, No. 4,pp. 330-336. 中文參考文獻 1. 王友亮,應用建築圖形元件於工程專案排程之研究,碩士論文,國立成功大學(2005) 2. 吳松駿,精實產品開發模式之建構,碩士論文,東海大學(2005) 3. 吳國棟,資料庫線上核發系統規劃研究-以C公司為例,碩士論文,大同大學(2008) 4. 吳聰敏,實獲值管理應用於營建工程專案成本管控之研究,碩士論文,國立台灣大學(2007) 5. 呂明娟,建築結構工程4D模擬系統之研究,碩士論文,國立臺灣大學(2006) 6. 林禾田,營造廠工程採購發包作業績效的影響因子,碩士論文,國立高雄第一科技大學(2005) 7. 拾景源,導入精實生產架構不同生產類型的彈性混線生產模式-以FA公司為例,碩士論文,清華大學(2008) 8. 柯韋如,營造廠執行專案採購精實管理之研究,碩士論文,國立台灣大學(2007) 9. 洪銘揚,營建工程知識管理系統架構之探討,碩士論文,台灣科技大學(2001) 10. 許平,中小企業導入精實生產和六標準差之可行性研究-以台灣中小型電鍍廠為案例,碩士論文,朝陽科技大學(2008) 11. 陳崇志,跨國光學企業導入精實生產績效差異之分析,碩士論文,東海大學(2005) 12. 曾守正,資料庫系統之理論與實務,儒林圖書,(1996) 13. 曾守正、周韻寰,資料庫系統進階實務,儒林圖書,(1999) 14. 曾國峯,建築工程3D施工順序模擬系統之研究,碩士論文,國立台灣大學(2007) 15. 黃建勝,製造商之採購管理行為對採購風險及生產績效之影響,碩士論文,銘傳大學(2004) 16. 葉建宏,以智慧資本評量高科技製造廠商採購管理之研究-以C公司為例,碩士論文,國立交通大學(2004) 17. 鄒郁菁,營造廠商電子詢報價系統規劃與實例,碩士論文,國立交通大學(2003) 18. 劉侑蒼,鋪面路網資料庫與地理資訊化系統架構之研究,碩士論文,國立中央大學(2004) 19. 潘稟嘉,建築圖形資訊標準於營建業電子商務之應用研究,碩士論文,國立臺灣大學(2000) 20. 鄭介旗,4D於困難施工對策研擬應用,碩士論文,國立成功大學(2005) 21. 鄧承根,專案工程監造作業資料庫建構及管理之研究--以軍事工程為例,碩士論文,國立中央大學(2006) 22. 盧中強,鋪面路網資料庫與地理資訊化系統架構之研究,碩士論文,淡江大學(2001) 23. 謝正鵬,結合精實生產與交易成本理論以改善台灣企業的成本競爭力以-台灣品牌液晶電視製造商為例,碩士論文,成功大學(2007) 24. 謝東穎,鋼結構工程4D模擬系統之研究,碩士論文,國立臺灣大學(2005) 25. 魏誥辰,應用多維度建築圖形元件於營建專案分包商資訊管理之研究,碩士論文,國立成功大學(2005) | |
dc.identifier.uri | http://tdr.lib.ntu.edu.tw/jspui/handle/123456789/43306 | - |
dc.description.abstract | 目前多維度圖形技術在土木工程領域,大多僅止於視覺方面展示,但於其他工程實務上的運用卻寥寥可數。而將其應用於專案物料採購上由於尚沒有統一且制式化的標準可供參考,缺乏系統化的概念,一般成效不彰,故思考如何適時將結合多維度圖形資料庫技術應用於物料採購,以便於採購管理並避免錯誤採購所造成之浪費,是激發本研究之動機。
本研究旨在導入精實採購的概念結合3D圖檔的特性,提供專案管理者一套採購管理的模式。本模式之架構為:(一)以Work Breakdown Structure (WBS)為基礎,發展以圖形為主之分工結構,稱為Object Block Work Breakdown Structure OBWBS(二)透過OBWBS的階層架構分解最小單位3D 圖形元件,並且附加相關材料屬性(例如:數量、型號等料單產出所需資訊)(三)依據精實採購原則,結合OBWBS之圖形關聯與WBS之工項關係,建構資料庫之基本架構與執行流程,以達到系統化採購管理之目標。 經由圖形元件與材料屬性的連結,將可迅速掌握建物的材料清單及採購資訊。期望經由不同專案資料的累積,建立可重複利用之樣版(Template),提供營造廠日後於相似建物上,能精確計算相關採購物料,將可為工程節省大量的時間、成本。 | zh_TW |
dc.description.abstract | Multi-dimensional graphic technology is mostly used in the visual display in the field of civil engineering currently, but applications on other projects practice are few. Because there is no standard and systematic protocol to follow, it is usually inefficient and time-consuming to apply the multi-dimensional graphic technology into the material procurement in construction projects. This research tended to apply lean procurement into the materials management and facilitate the procurement management to avoid the waste cause by inaccurate procurement.
This research combined 3D images characteristics with lean procurement to create a procurement management model for project manager. The steps of building this model are: (a) Developing a graphical framework which is called Object Block Work Breakdown Structure (OBWBS) based on Work Breakdown Structure (WBS) (b) Decomposing the hierarchy structure of OBWBS to produce the smallest 3D graphical unit with relevant material properties (example: the information is needed by the bill of material, such as number and models, etc. ) (c) Constructing basic structure and implementation process of the database associate with graphic correlation of OBWBS and work relationship of WBS to achieve the goal of systematic procurement management. By applying the graphical database which consists of graphical components and material properties, project manager can easily realize the bill of material and other procurement information. Furthermore, establishing reusable template through accumulation of different projects data can provide construction companies with accurate calculation related to the procurement of materials on similar type of building, it be able to save a lot of time and cost of projects in the future. | en |
dc.description.provenance | Made available in DSpace on 2021-06-15T01:48:31Z (GMT). No. of bitstreams: 1 ntu-98-R96521710-1.pdf: 2600000 bytes, checksum: fcb172c8557d62eaa0ec467212354721 (MD5) Previous issue date: 2009 | en |
dc.description.tableofcontents | 口試委員審定書 I
誌謝 II 摘要 III ABSTRACT IV 第一章 緒論 1 1.1 研究動機 1 1.2 研究目的 2 1.3 研究範圍與限制 2 1.4 研究流程與方法 3 1.5 論文架構 4 1.6 小結 4 第二章 文獻回顧 6 2.1 精實管理 6 2.1.1 精實生產 6 2.1.2 精實思維 7 2.1.2.1 精實思維之源由 7 2.1.2.2 精實思維之五項原理 7 2.1.3 精實營建 9 2.1.3.1 營建工程相關浪費彙整 9 2.1.3.2 精實營建理論 10 2.1.4 精實採購流程 11 2.2 4D模型相關應用 14 2.2.1 4D模型 14 2.2.2 4D互動式資訊場 15 2.2.3 視覺化比較 17 2.2.4 圖檔資訊解析技術 19 2.2.4.1 以工作單元(Work Package)解析圖檔 19 2.2.4.2 以作業項目(Work item)解析圖檔 20 2.2.4.3 以工地管控解析圖檔 21 2.3 資料庫 22 2.3.1 資料庫之定義 22 2.3.2 資料庫主要形式 23 2.3.3 元件資料庫 25 2.3.3.1 建築元件資料庫 25 2.4 小結 26 第三章 圖形介面劃分及應用 27 3.1 專案分工結構圖解析 28 3.1.1 建築元件庫(Building component Library, BCL) 28 3.1.2 Work Package Model 30 3.2 劃分原則 31 3.2.1 WBS(Work Breakdown Structure) 31 3.2.2 OBWBS(Object Block Work Breakdown Structure) 32 3.2.3 RBS(Resource Breakdown Structure) 34 3.3 賦予圖塊資訊 35 3.3.1 賦予採購資訊 35 3.3.1.1 圖塊及材料名稱、屬性分類 36 3.3.2 圖塊編碼及位置 37 3.4 小結 37 第四章 圖形資料庫模組建立 38 4.1 資料庫建置流程 39 4.2 多維度圖形資料庫建置步驟 42 4.2.1 精實採購 42 4.2.2 ER-MODEL建置 45 4.2.3 資料庫模組整合 46 4.2.4 Microstation Triforma 47 4.2.5 Microsoft Access 49 4.3 圖形資料庫應用 51 4.3.1 情境模擬案例導入 52 4.3.1.1 案例介紹 52 4.3.1.2 3D圖檔分解 52 4.3.1.3 查詢介面應用 55 4.4 圖形資料庫問題與困難點 62 4.5 小結 63 第五章 結論與建議 64 5.1 結論 64 5.2 未來研究與建議 65 參考文獻 67 | |
dc.language.iso | zh-TW | |
dc.title | 應用多維度圖形資料庫技術於精實採購之研究 | zh_TW |
dc.title | Application of multi-dimensional graphic database for lean procurement | en |
dc.type | Thesis | |
dc.date.schoolyear | 97-2 | |
dc.description.degree | 碩士 | |
dc.contributor.oralexamcommittee | 張陸滿(Luh-Maan Chang),林保宏(Pao-Hung Lin),陳士明(Shih-Ming Chen) | |
dc.subject.keyword | 多維度圖形,WBS,精實採購,資料庫, | zh_TW |
dc.subject.keyword | Multi-dimensional graphics,WBS,lean procurement,database, | en |
dc.relation.page | 70 | |
dc.rights.note | 有償授權 | |
dc.date.accepted | 2009-07-07 | |
dc.contributor.author-college | 工學院 | zh_TW |
dc.contributor.author-dept | 土木工程學研究所 | zh_TW |